Rows:
a. Field Work & Site Surveys: Identify the costs for all necessary Field Work and Site Surveys, including data collection.
b. NEPA & Sec. 7 ESA Consultation: Identify the costs for completing NEPA and Section 7 ESA Consultation.
c. Permit Acquisition: Identify the costs for acquiring all required permits for project implementation.
d. Project Design & Engineering: Identify the costs for Project Design and Engineering support.
e. Contract Preparation: Identify the costs for developing necessary contracts for advertisement and award, including costs for Forest Service contracting officer support. and contracting officer representatives if necessary.
f. Contract Administration: Identify the costs for administering all necessary contracts, including costs for Forest Service contracting officer support and contracting officer representatives if necessary.
g. Contract Cost: Provide an estimate for the actual Contract Cost.
h. Workforce Cost: Provide an estimate for the actual Workforce Cost.
i. Materials & Supplies: Identify the costs associated with all Materials and Supplies necessary to complete the project if not already included in contract costs.
j. Monitoring: Identify the costs to complete the required Monitoring components outlined in the Monitoring Plan, below, for Item 21.
k. Other (specify): Identify any other costs associated with the project and specify.
l. Project Sub-Total: The sum of Cost Items a. through k.
m. Indirect Costs: Include a standard indirect cost (overhead) rate of 12.5% applied to the Project Sub-Total. For multi-year funding requests, the total amount of Indirect Costs for the entire project should be reflected.
n. Total Project Cost Estimate: The sum of Project Sub-Total (Cost Item l.) and Indirect Costs (Cost Item m.).